Production of products is done in a very systematic manner. The orders of various customers are planned for production month wise for which a production plan is issued to Works as per delivery schedules of our various customers. A regular follow up of production activities/progress is done every week or as per emergence requirements through Production Review Meetings to ensure monthly sale targets.

 

Raw Material:
Our Material management department as indicated in our monthly production plan procures raw material. All the raw materials are procured from approved suppliers/manufacturers only. The major suppliers of raw material include M/S Steel Authority of India Ltd., Upper India Steel, Modern Steel, Vardhman Special Steels Ltd., Vishavkarma Steel, Mukand Steel, Ludhiana etc. All these manufacturers produce M.S. and Alloy Steel Flats, Rounds, Squares and Hexagon sections under strict quality norms as per relevant ISS/BSS/DIN/ASTM specifications and are well equipped with in-plant material test facilities for Chemical and Mechanical properties. The major lots are accompanied with manufacturer’s test certificate bearing Heat No. And colour code as per relevant specifications.

These raw materials are again tested for Chemical properties in our own test lab. to verify the values of various elements given by the manufacturer of Iron and Steel. On verification of Chemical properties, an identification (Q. No.) is marked on the lot of material tested and a document is generated for the same which is transferred to ‘Job Route Card'(Annex. A). A stock register is maintained for the receipt and issue of raw materials for various items as per requirements indicated in the Job Route card as per specimen. Different grades of raw material are stacked at appropriate places earmarked for the purpose to avoid any mix up. Proper colour codification is maintained at all stages.

  1. The manufacturing process of Bolts Screws consists of blank cutting from round bars, forging / upsetting head by cold / hot process depending on size, trimming, facing, centreless grinding of shank, thread rolling, annealing, hardening, tempering, cleaning, plating, dispatch.
  2. The manufacturing process of Nuts consists of blank cutting from round bars on Auto/ Semi auto Nut cutting machines or hot / cold forgings depending on size, chamfering, tapping, annealing, hardening, tempering, cleaning, plating, dispatch.
  3. The manufacturing process of Studs consists of blank cutting from round bars, facing, chamfering, centreless grinding of shank, thread rolling, annealing, hardening, tempering, cleaning, plating, dispatch.
  4. The manufacturing process of Washers consists of blank cutting from round bars on automats, facing, chamfering, hardening, tempering, cleaning, plating, dispatch.
  5. The manufacturing process of Nuts by Cold forming process consists of feeding the rounds in coils in the imported Nut formers, which automatically forms the shape of a Hex/Flanged Nut/Weld Nut after passing through six inbuilt stations. These Nuts are then tapped in the Automatic Nut tapping Machines.

 

A specific Quality policy exists in out unit. It is clearly defined to check the products at various stages of manufacture and at the end of all operations. It is ensured both by the workmen and quality staff on duty for this purpose. To achieve this aim and make a foolproof system, a Job Route Card (Annexure ‘A’) on the. Basis of Quality Plan (Annexure ‘C’) is introduced while launching the production of each item and stage inspection is carried out during each operation/after each operation on sampling basis as per Sampling Plan for Threaded Fasteners, I.S. 2614 by the concerned workmen and counter checked by QC staff.

During the manufacture of items, if any dimensions is not confirming to drawing, a Non conformity Report (NCR) is prepared and corrective action is taken then and there. Since ours is a mass production producing unit, sizes are thoroughly checked during the setting of the job as such negligible NCR’s are raised. Quality control staff has the authority to stop the operation if any deviation in dimensions/process is observed at any stage of manufacture. Work is allowed to proceed further only after the necessary corrective action is taken.

The movement of material during various processes is strictly restricted in “BINS” specially employed for this purpose along with Job Route Card to avoid any mix up of various products and strictest quality control is maintained for all dimensions/processes. At the end of all the processes, final inspection is done by the Quality staff as per Sampling Plan for threaded fasteners I.S. 2614 and an Observation sheet is generated as per specimen enclosed as Annexure ‘D.’ Thus the following documents are maintained for each item.

  1. Job Route Card duly certified by QC staff.
  2. Observation sheet duly certified by QC staff.
  3. Test certificate for Chemical/Mechanical Properties as per requirements of Customers duly certified by QC staff. The copy of the test certificate is sent to the Customer along with dispatch documents.

All the above documents are maintained by QC staffs, which are easily retrievable. These documents are normally retained for a period of three years.

After the material is cleared for dispatch by QC staff, the same is handed over to our Dispatch section who. Pack the material in standard Card boxes/cartoons or as per specific requirements of the customers after applying Anti corrosive oil. These card boxes/cartoons are then dispatched in Wooden boxes. Each box is identified with Size, grade and quantity of product. The records of receipt and issue of. finished goods is kept by the dispatch section. The stock items are properly identified for Size, grade and quantity and a proper record is maintained Rack/Box wise. The Stock is periodically reviewed for its correctness and quality.

Thus a total quality environment exists in our unit which has led to a wide acceptability of our products among various Govt. Organization/Public Sector Organizations/Private Large Scale Industries/our Authorized and registered dealers allover the country and International Market through Export Houses. We are proud of our achievements and total Quality Product.

 

PROCESS

SIZE

QTY.

CHECKED

STAGE  INSPECTION STATUS

REMARK

SIGN

Blank cutting

 

 

ACC./RWK/REJ.

 

 

Forging (size Identification)

 

 

ACC./RWK/REJ.

 

 

Trimming

 

 

ACC./RWK/REJ.

 

 

Facing

 

 

ACC./RWK/REJ.

 

 

Grinding

 

 

ACC./RWK/REJ .

 

 

Thread Rolling

 

 

ACC./RWK/REJ.

Check with

Gauge,Yes/No

 

Drilling

 

 

ACC./RWK/REJ.

 

 

Heat Treatment

Temp.

 

Hardness Observed

Stage Inspection Status

Sign

Hardening

 

Soaking Period

 

ACC./RWK/REJ

 

Quenching

 

Air/water/Oil

 

ACC./RWK/REJ

 

Tempering

 

Soaking Period

 

ACC./RWK/REJ

 

Magnaflux crack detection

 

Yes/No

 

ACC./RWK/REJ

 

 

Plating :Zinc/ Auto Black/ Phosphating /E.T./Hot Dip Galv./Cadmium

Cleaning  Yes/ No.

Operation

Characteristic

Type of check

Quantum

Document Ref.

Norms of acceptance

Record Format

Raw Material

Chemical Analysis

Chemistry as per relevant grade

Onesample /heat/lot

Relevant Standard

Relevant Standard

Test Report

 

Mechanical Properties

UTS,YS,%Elong

-do-

-do-

-do-

Test Report

Forgings

Dimensions

Major Parameters

2%

-do-

-do-

Process Obs.Sheet

Rough Machined Bolt/Nut

Dimensions

Major Parameters

2%

-do-

-do-

Process Obs.Sheet

Heat Treatment

Annealing,Hardening&Tempering

Hardness

5%

-do-

-do-

Process Obs.Sheet

 

Mechanical Properties

UTS,YS,%elong.Proof Load test for Nuts only

<M36

One Sample/Dia.

-do-

-do-

Test Report

 

Surface discontinuity threads

MPI test Size with Ring/Plug Gauge

5% or SOS 5%

-do-

-do-

-do-

Job Route card

Process Obs.sheet

Plating

Depth of plating

As per requirement

1or2 Pcs/lots

-do-

-do-

Job Route card

Final Inspection

Dimensional and Review of Test reports

All Parameters as per Drg./Standards

As per sampling plan

-do-

-do-

Observation Sheet /Job Route Card.